Timeline

  • 2009 – Started monitoring wind speed.
  • 2016 March – Landowners signed agreements to host the wind farm.
  • 2016 March – Completion of all studies.
  • 2016 July – Submission of planning application to the Victorian Minister for Planning.
  • 2016 November – Planning permit issued.
  • 2017 December – Power Purchase Agreement signed with Telstra.
  • 2017 December – Contracts signed with Senvion Downer and AusNet for construction.
  • 2018 March – Commencement of Stage 1 construction (See detailed Stage 1 construction timeline in the April 2018 Newsletter).
  • 2019 August – Expected completion of Stage 1.